Feasibility study Poppodium Boerderij
Poppodium Boerderij is an important pop venue for Zoetermeer, but it also attracts regional, national and international visitors. To maintain Boerderij's good position, expansion and further professionalization are needed. The capacity of the venue (maximum 750 visitors) is too small and the current building is not suitable for new developments.

In 2024, the municipality drew up a business plan in consultation with Boerderij. The plan focuses on Boerderij's desired expansion to include a large hall for up to 1,300 visitors, with 250 seats. In addition, there will be a small hall for 400 visitors and a Podiumcafé for 200 visitors. The Casa coffee shop and rehearsal rooms will also move to the new building. The new building will be located between Gymworld and the current Boerderij.
The growth in visitor numbers is estimated at approximately 50,000 now, rising to over 113,000 per year once the new Poppodium building is complete. The program will be expanded to include indoor festivals, major and upcoming Dutch artists, educational activities, and talent development in collaboration with schools and music schools in the city. For talent development, it is also important that the rehearsal rooms currently located in the Boerderij building are included in the new construction.
City Council Decision February 17, 2025 Credit Application
- On February 17, 2025, the city council approved the municipal executive's proposal to allocate funds to investigate the feasibility of the plans for Poppodium Boerderij. The municipality then commissioned a feasibility study for two different new-build options. An external agency, in consultation with Poppodium Boerderij, drew up a list of requirements that the new building must meet. Below is a link to the documents.
- Council proposal for credit application for feasibility phase
- Process proposal for participation in Poppodium Boerderij
- Council memo on the status of the Boerderij music venue
More time than expected was needed to finalize the requirements program. Here you will find the memo to the city council dated June 24, 2025, on this subject. It states that the municipality, in collaboration with Poppodium Boerderij, has continued to work on a carefully drafted program of requirements for the new building. This will serve as the basis for the further development, tendering, and realization of Poppodium Boerderij.
City Council Decision November 24, 2025 New construction option selection
In the fall of 2025, the city council decided on the feasibility of the plans and chose between the different options: a flat option and a stacked option, each with different sustainability ambitions. On November 24, 2025, the city council unanimously approved the preferred variant A, the halls of the Boerderij and the podium café on the ground floor with a lower sustainability investment. View the entire council document here . This means that the tender for an architect can now be started and the preconditions for the project, such as parking and access to the building, can be addressed together with the Voorweg Centrum project.
Participation with local residents
The participation process proposal adopted by the municipal council in early 2025 states that, once a preferred option has been selected, a participation meeting will be organized for residents. However, we are unable to provide much visual information at this stage. We have therefore decided to limit participation to the surrounding area once an architect has been appointed to make actual changes or adjustments to the building or its accessibility. This is expected to take place around the summer of 2026.