New school building and new sports hall at Van Doornenplantsoen
The municipality of Zoetermeer is building a new school building for the MOTION Beweeg College and a new municipal sports hall at Van Doornenplantsoen.
MOTION Move College
Following the administrative takeover by the Lucas Education Foundation, the name of this vmbo school has changed. The new name better reflects the current direction and needs of the school.
The current site is severely outdated and far too large. The new school can accommodate up to 550 students. The Program of Requirements 'Fresh Schools 2021' is a basis for building a new school. This establishes good and appropriate educational quality in a fun, healthy, inspiring and sustainable environment. A Fresh School pays attention to the themes: energy, air quality, temperature, light and sound.
Sports Hall
In the coalition agreement 'Doing together what is necessary' it was agreed to invest in sports facilities. The new sports hall is being built because of the shortage of sports halls in Zoetermeer.
The new sports hall will be used by the schools during the day. In addition, the Zoetermeer sports clubs will also use the hall. A number of common areas will be shared with the MOTION Beweeg College (entrance, checkroom, changing room, toilets). Thanks to this collaboration, the sports hall will be used optimally.
Larger sports hall for more opportunities
During the design process, the "Quality Standards for Indoor Sports Facilities Korfball" were modified and further explained. As a result, the dimensions of the playing field, including free range, were revised.
By enlarging the sports hall by about 400m2, we will make it suitable for more sports and ensure that it meets the official rules of the Royal Dutch Korfball Association (KNKV). The expansion also provides several improvements in the surrounding areas:
- Spacious locker rooms that are better laid out and more user-friendly;
- Two locker rooms for teachers instead of one;
- Enlarged equipment storage, providing more storage space and more options for use of the hall and sports classes;
- A built-in trampoline;
- An additional changing area for the disabled (MIVA);
- A separate first aid room;
- Additional (rentable) accommodation space of 80m2;
- A spacious entrance overlooking the hall;
- An elevator with access to the elevated schoolyard.
The council unanimously approved the enlargement of the sports hall on Sept. 16, 2024.
Design phase
The final design is almost complete, and the architect is working on the final details. The images at the bottom of this page give a good idea of the design of the school and sports hall. Please note that these images are not quite final yet, as the architect is still adjusting the facade. The updated facade drawings will be added to this page later.
New zoning plan
The school and sports hall will be built on the grassy field opposite the existing school. A new zoning plan has been drawn up for this purpose. On Monday, Oct. 23, 2023, the council proposal for the adoption of the zoning plan for the new Van Doornenplantsoen building was adopted, changing the zoning.
Environmental Permit
The environmental permit has been applied for and is currently (October 2024) pending.
Start of construction - information evening
After obtaining the environmental permit, the contractor can start work to actually build the school and sports hall. Prior to the start of construction, the immediate area will be invited to an information evening where information on construction, safety, and site layout, among other things, will be shared.
Planning
- Elaboration of final design - April to June 2024
- Environmental permit application - June/July 2024
- Construction start - first quarter 2025
- Completion - second quarter 2026